Priced at US$1.63bn (in 2015), the Orange Line Metro Train (OLMT) project in Lahore was one of Pakistan’s earliest (and costliest!) transport infrastructure megaprojects ever undertaken. Devised to ease congestion in Lahore, promote ecofriendly, efficient, modern and affordable transport systems and lead to improved mobility across Lahore, the OLMT was a socially, politically and economically important project.The case is seen through the eyes of the protagonist, Uzair Shah, a seasoned public servant and an experienced Transport Engineer. At the time of the decision, Shah was General Manager – Operations at the newly established Punjab Metrobus Authority (PMA – the project sponsor) and was also the project lead of OLMT’s Project Management Unit (PMU). Through Shah’s eyes, students approach the project at a juncture when the most serious contractual dispute in the project’s history has erupted. The parties at the interface were Lahore Development Authority (LDA), PMU’s technical interface with contractors and consultants and Maqbool-Colson Joint Venture (MCJV), one of the two civil work contractors hired for OLMT’s civil works.While quality issues had been emerging with MCJV for a few months, LDA had maintained unilateral communications and remained considerably adversarial in their dealings with MCJV. Eventually, in October 2016, this relationship had soured to such an extent that it appeared irreconcilable. It was only then that LDA had recommended Shah to take the contractor to court for non-performance.The decision that Uzair faced was whether to take LDA’s advice and take the contractor to court (terminate the contract, claim performance guarantee and appoint a new contractor) or negotiate and continue with the current contract. The decision had huge financial, legal, reputational, political and schedule-related implications. The decision needed to be taken by the protagonist in the context of all these factors.