MORESA S.A.S was a family company founded in 1994, whose value proposition focused on construction and permanent advice for the execution of innovative and contemporary projects with more than 27 years of experience in the city of San José de Cucuta, department of Norte de Santander, Colombia. The objective of the case is to Relate risk as one of the 12 principles in project management contemplated in the international standards of the PMBOK Seventh Edition guide; Determine high-level risks by articulating the WBS and RBS of a construction project; Perform a qualitative and quantitative analysis of the probability and impact of risks through the heat map tool and the Expected Monetary Value (EMV) technique and propose the different response strategies contemplated in the risk management through the formulation of a response and contingency plan. The teaching case is designed for academic programs in areas of knowledge of civil engineering, architecture and at postgraduate level such as: Master’s in civil engineering, Master’s in risk management, Master in project management or MBA. For this case, an expert judgment was developed with professionals belonging to different areas of knowledge. Likewise, secondary information was collected from the organization's strategic documents and the analogous estimation through the historical records of the project portfolio developed by the construction company. Finally, the case, classified in the Built Environment, a challenge that project managers must face in VUCA environment through risk management.